Conwy Local Development Plan 2007 - 2022
Appendix 1
5.1 Implementation Plan
5.1.1 Under the new planning system the Local Development Plan is intended to be a responsive, dynamic document which has a focus on implementation and achievement in place-shaping. As such, the framework for implementation of policies and proposals and mechanisms for monitoring achievement are critical to the success of the Conwy LDP.
5.1.2 This section outlines how the LDP policies will be implemented in the context of infrastructure constraints and how the aims and objectives will be monitored. Many of the policies in the LDP will be implemented through other Development Plan Documents such as the Colwyn Bay Masterplan. The Conwy Community Strategy – One Conwy, the Local Service Board (LSB) and key partners will also play a significant role in the delivery of the policies in the LDP. The key agencies and partners likely to have a role in the delivery of the policies are identified in Table 15.
5.1.3 The presence of clear mechanisms for implementation and monitoring forms part of the test of soundness of the LDP. Monitoring helps to answer several key questions:
- Are policies achieving their objectives?
- Have policies had unintended consequences?
- Are the assumptions and objectives behind policies still relevant?
- Are the desired outputs being achieved?
5.1.4 In order to assess the effectiveness of the policies in the delivery of development and protection of the environment, it is important that continuous monitoring and review of policies in the Local Development Plan is undertaken throughout the Plan period. Monitoring and review will take place on an annual basis through the Annual Monitoring Report (AMR). If, as a result of monitoring and review, it appears that policies and allocations are not being met and development is not coming forward in a sustainable or timely manner, the Council will be proactive in using its powers to respond to changing circumstances. The following mechanisms can be triggered:
- Actions to bring forward sites for development, wherever possible, in partnership with landowners and developers;
- Action to bring forward development sites on previously developed land;
- Use of Compulsory Purchase Orders to unlock sites;
- Working with partners to bring forward investment in infrastructure;
- Review of land allocations or policies in the Local Development Plan.
5.1.5 Implementing the phasing policies, to enable the plan, monitor and review approach will be used to guide the phasing of development and performance against the previously developed land target. Where monitoring shows that sites are not coming forward as anticipated, other sites will be brought forward in the programme, having particular regard to the priority for previously developed land. If land supply significantly exceeds estimated take up rates it may be necessary to refuse applications until the Plan is reviewed. It will also be necessary to guide windfall development, in particular where there is clear need for affordable housing, to settlements in need over the Plan period.
5.1.6 The Council will prepare Development Briefs for new major housing sites (50 dwellings or above) and employment sites (5 hectares and above) The purpose of a development brief is to inform developers and other interested parties of the constraints and opportunities presented by a site and the type of development expected or encouraged by local planning policies within this LDP. Development Briefs will be used to set out more detailed information regarding phasing of different parts of the site, where it is favourable to commence development on one part of the site in preference to another due to access or other constraints.
5.2 Responding to Delivery Issues
5.2.1 In the event that the Annual Monitoring Report identifies delivery issues in relation to the development strategy, where key policy targets are not being met, these would need to be assessed as part of the Annual Monitoring Report process and a decision reached on whether any change was required to the LDP, or through other mechanisms.
5.2.2 A key aspect of monitoring the Conwy LDP is the number of homes being built. The number of homes coming forward in Conwy, in the urban accessible locations, will need to be assessed in the Annual Monitoring Report. Other policies will also be monitored at relevant spatial levels in the settlement hierarchy, or as appropriate to the specific policy.
5.2.3 The survey results from BP/31 – ‘Capacity of the House Building Industry’ indicate that developers could build up to a maximum of 75 dwellings per annum during the Plan period on any one site and dependant on the number of developers building on site. The results of this survey have informed the phasing of sites in Table 11.
5.2.4 Whilst it is not anticipated, if the situation were to arise where delivery in the priority urban development areas could not meet the housing needs of the area, this would trigger mitigation, as highlighted in the implementation plan (Table 15), with the identification of contingency sites allowing extra capacity to be brought forward if necessary. The proposed basis for the release of contingency sites is detailed in BP/41 – ‘Release of Contingency Sites’.
5.2.5 Where infrastructure capacity issues are highlighted, developer contributions and funding will ensure delivery of the sites as detailed in the next section.
5.3 Constraints on Development
5.3.1 A key factor in the successful implementation of the LDP is the infrastructure required to bring forward development. There is widespread acknowledgement that past public under-investment has lead to pressure on a range of public utilities across the country. In Conwy, key infrastructure constraints include poor public transport in some locations, limited sewage treatment works capacity and energy supply in rural areas and the lack of open space. This follows consultation with infrastructure providers in developing the LDP.
5.3.2 Following this consultation, it is apparent that there are no capacity issues for education and health provision. The issues raised by infrastructure providers have been taken into account in the development of the LDP, however, there remain outstanding issues that lead to a requirement to phase new development in order to ensure that it is not built / occupied until the infrastructure is available.
5.3.3 Where issues are apparent with capacity, developers will be subject to meeting those capacity issues through developer contributions in line with Policies DP/4 – ‘Development Criteria’ and DP/5 – ‘Infrastructure and New Developments’. The main general constraints affecting delivery of sites are outlined below, with Tables 11 and 12 providing detail on a site-by-site basis.
Constraints on access
5.3.4 All sites will require some works to access, in the form of constructing estate roads or junctions on to existing highways. Some sites require more significant work, which must be considered when phasing their development. This may be in the form of road widening, improving visibility at a junction or changes of levels on steeper ground.
Constraints on services to a site
5.3. A lack of services to a development site, in particular in the form of capacity constraints on sewerage networks or waste water treatment works will delay development. If the development is to go ahead, but improvements are not scheduled within Welsh Water’s Capital Investment Programme, then the cost of the necessary improvements will have to be borne by the developer.
Constraints on flood risk
5.3.6 If a site is at risk of flooding, it will often mean that development cannot take place, or will be restricted to those parts of the site outside the flood risk zone. On some sites, development may be allowed if mitigation methods are implemented. Further detail on flood risk within the Afon Conwy and Afon Clwyd areas can be found in BP/17 – ‘Strategic Flood Risk Assessment’.
Constraints on site availability
5.3.7 Some sites are suitable for development, however, are not immediately available because of current uses on the site. If the current occupiers have a timescale for vacating the site, for example if a lease is due to expire within the Plan period, then this is shown in table 11.
5.3.8 In some circumstances, a compulsory purchase order (CPO) may be required to enable a development to proceed. In this situation, a minimum of six months should be allowed, or for more complex developments, and with objections leading to public inquiry, 12 – 18 months is a more appropriate timescale.
5.4 Conwy Housing Delivery and Phasing Plan
5.4.1 Housing provision, particularly AHLN is a key priority of this Plan. As evidenced in BP/9 – ‘Affordable Housing Viability Study’ and set out in HOU/2 – ‘Affordable Housing for Local Need’, all housing allocations and new applications will be required to achieve the required level of affordable housing Policy HOU/2 is flexible enough to encourage developers to submit evidence base where they feel that the maximum level is unviable.
5.4.2 The priority for the Council is to make affordable housing provision on-site. However, in exceptional circumstances, payment of a commuted sum will be acceptable, as detailed in Policy HOU/2. To ensure delivery of affordable housing in areas of need, commuted sums will be delivered Plan Area wide as detailed in the Council’s adopted ‘Commuted Sums Protocol’.
5.4.3 In order to ensure that approximately 6,520 (478dwellings a year) dwellings are built in the County by 2022 it is necessary to identify the varying sources of additional housing and devise policies and proposals which will facilitate its provision. A housing delivery and phasing plan has been produced for the LDP which sets out an indicative assessment of annual build rates for the period up to 2022 to demonstrate a 15 year supply for Conwy. The plan has been prepared in support of the housing policies within this LDP but will also be updated through the preparation of the Conwy Annual Monitoring Report (AMR). An element of contingency (approximately 10%) has been applied to the Plan to take account of housing development which may not come forward over the Plan period (Table 12).
5.4.4 Recent completions and projected completion rates for sites currently with planning permission provide an important contribution to the housing supply. These are demonstrated in BP/5 – ‘Housing Land Availability Study’, BP/21 – ‘Site Deliverability Assessment’ and BP/30 – ‘Phasing Plan’.
5.4.5 Table 11 which follows comprises a Housing Delivery and Phasing Plan which illustrates how the allocated housing supply will contribute to provision and when it is expected that development will occur, with priority given to Previously Developed Land in a settlement. Annual review will allow the Council to monitor progress and identify any need to intervene. The trigger points for such intervention are detailed in Policy HOU/1 and the Implementation & Monitoring Section.
5.5 Phasing of Development and Contingency Sites
5.5.1 As a result of the above capacity constraints in some areas, the priority for Previously Developed Land and AHLN delivery, there is a need to phase residential development in order to ensure that the supporting infrastructure is available. However, if the situation alters there may be opportunity to bring development forward earlier than anticipated. Further, there may be instances where the developer is able to address deficiencies to overcome the problem. More detailed site specific phasing work is set out in BP/30 – ‘Phasing Plan’.
5.5.2 The Housing Delivery and Phasing Plan, comprising the trajectory below and Table 11, show the approach taken to the phasing of new residential development. The Plan assumes that during the first part of the Plan period, dwelling completions will comprise mainly the development that already has planning permission. An explanation of the housing completion and commitment figures is available in BP/4 – ‘Housing Land Supply’ and BP/21. It is anticipated that the AHLN delivery will be less in the short term of the Plan due to commitments and greater in the medium to long term when windfall and new allocations come forward.
5.5.3 In addition to ensuring that essential site requirements come forward as a priority, the phasing plan has also been designed with the aim of ensuring a constant 5 year housing land supply.
5.5.4 While, as reference previously, the Council considers that its housing allocations in the Plan are deliverable within the Plan period, a 10% contingency has been applied to the Plan to take account of unknown constraints which may prevent some allocated sites being developed within the period.
5.5.5 Table 12, therefore, comprises a list of additional housing ‘contingency sites’ which will be held in reserve but which can be released for development on a managed basis should plan monitoring following adoption indicate that the allocated housing sites in the Plan are not coming forward for development as anticipated in the Plan.
5.5.6 Where the JHLAS demonstrates that the Council is unable to achieve a five year housing land supply, the Council will release a site (or sites) from the list of contingency sites in Table 12, to increase the housing land supply and assist in meeting the identified shortfall.
5.5.7 The release of contingency sites will be based on a range of criteria including location, size and deliverability (as detailed in Policy HOU/1) in the context of the Plan’s priorities and indicators.
Table 11 Conwy Housing Delivery and Phasing Plan: Allocated Sites
Phasing of allocated sites:
i = projected completions 01/04/2007 – 31/03/2012
ii = projected completions 01/04/2012 – 31/03/2017
iii = projected completions 01/04/2017 – 31/03/2022
URBAN DEVELOPMENT STRATEGY AREA | ||||||||
---|---|---|---|---|---|---|---|---|
Site Ref | Site Name | Area (ha) | Number of units | PDL status | Planning status | i | ii | iii |
Abergele | ||||||||
79/80/81/82/E3 | Rhuddlan Rd, Tandderwen Farm | 25.5 | 600 | Green | Part of site at risk of flooding; mitigation required on parts of site as set out in the SFCA. | 150 | 450 | |
Traffic management improvements may be required for all phases. Prior to development, Transport Assessments will determine if contributions are necessary towards a Traffic Improvement Scheme | ||||||||
Improvements to sewerage network required. High pressure gas pipeline crosses the Southern part of the site. | ||||||||
481 | Abergele Business Park | 5 | 200 | Brown | Traffic improvements may be required. Prior to development, Transport Assessments and then on-going annual monitoring of the traffic flows within the town will determine if contributions are necessary towards a Traffic Improvement Scheme. | 200 | ||
Colwyn Bay, Rhos on Sea | ||||||||
217 | BT Exchange | 1.21 | 70 | Brown | Lease extended on site; not available until approx. 2015. | 70 | ||
494 | Ysgol y Graig, Old Colwyn | 1.18 | 30 | Brown | Junction improvements required. | 30 | ||
488 | Lawson Road | 0.53 | 35 | Brown | No major constraints | 35 | ||
67 | Glyn Farm, Colwyn Bay | 3.2 | 39 | Green | New water main required | 39 | ||
247 | Dinerth Road, Rhos on Sea | 1.81 | 65 | Brown | Lease on site (Council owned)) | 30 | 35 | |
71/348 | Dinerth Hall Farm, Rhos on Sea | 2.7 | 80 | Green | Part of site C1 flood risk zone, therefore should be avoided as set out in the SFCA. Traffic study to assess extent of junction and access improvements. Improvements to water supply needed | 80 | ||
496 | Ty Mawr, Old Colwyn | 12.64 | 255 | Green | Junction improvements required with additional local parking | 50 | 205 | |
Conwy, Llandudno Junction, Llandudno | ||||||||
14 | Woodland, Llandudno Junction | 1.92 | 75 | Green | Part of site C1 zone, & development in this area should be avoided, as set out in the SFCA | 75 | ||
434 | Plas yn dre | 0.22 | 40 | Brown | Site C1 flood risk, therefore some mitigation may be required as set out in the SFCA. | 40 | ||
449 | Plas Penrhyn, Penrhyn Bay | 0.67 | 30 | Brown | No major constraints | 30 | ||
176 | Esgyryn, Llandudno Junction Mixed use housing, employment, community facilities | 9.8 | 120 | Green | Improvements to sewerage network required including the introduction of sustainable urban drainage ponds | 70 | 50 | |
439 | Social Club, Llandudno Junction | 0.98 | 40 | Brown | Partly in C2 flood zone; some mitigation may be required as set out in the SFCA. | 40 | ||
Sewerage network overloaded | ||||||||
Llanfairfechan, Penmaenmawr | ||||||||
31 | Adjacent to Glanafon, | 0.22 | 15 | Green | Part of site C2 zone, therefore this area should not be developed as set out in the SFCA. | 15 | ||
Currently unavailable due to lease; likely to become available later in Plan period. | ||||||||
429 | Dexter Products | 0.47 | 15 | Brown | Footway improvements to Llanerch Road are required | 15 | ||
521 | West Coast Building, Llanfairfechan | 0.24 | 10 | Brown | No major constraints | 10 | ||
Llanrwst | ||||||||
287 | Bryn Hyfryd, Ffordd Tan yr Ysgol | 1.17 | 40 | Green | Site is subject to flood risk; land raising required as set out in the SFCA. Drainage must be considered during the layout and design planning stage of site development to ensure adequate measures are provided for sustainable drainage systems | 40 | ||
Any development will require adequate provision be made for increase in traffic. | ||||||||
Improvements needed to sewerage network and sewage works. | ||||||||
455 | Site A, North of Llanrwst | 2.06 | 50 | Green | Improvements needed to sewerage network and sewage works. | 50 | ||
458 | Site D, East of Llanrwst | 1.7 | 60 | Green | Part of site in C2 & this area should not be developed, as set out in SFCA. Access through site 287 with the same requirements. Improvements needed to sewerage network and sewage works. | 60 | ||
459 | Site E adj. Bryn Hyfryd | 1.42 | 50 | Green | Part of site in C2 & this area should not be developed as set out in SFCA. Access through site 287 with the same requirements Improvements needed to sewerage network and sewage works. | 50 | ||
RURAL DEVELOPMENT STRATEGY AREA | ||||||||
Main villages: Tier 1 | ||||||||
Dwygyfylchi | ||||||||
56 | Off Ysguborwen Road | 0.5 | 15 | Green | No major constraints | 15 | ||
53 | North of Groesffordd | 1.12 | 30 | Green | No major constraints but improvements to site access | 30 | ||
Glan Conwy | ||||||||
270 | Top Llan Road | 4.45 | 80 | Green | Development should involve realignment of junction. | 20 | 60 | |
Improvements to sewage network required | ||||||||
Llanddulas | ||||||||
403 | South of the Mill | 0.83 | 20 | Green | Access only through site 406. | 20 | ||
406 | Pencoed Rd | 0.85 | 20 | Green | Improvements to both vehicular and pedestrian access may be required. | 20 | ||
Llysfaen | ||||||||
87 | Adjoining former rectory, | 1.04 | 30 | Green | No major constraints | 30 | ||
160 | Adjoining Ysgol Cynfran | 1.3 | 40 | Green | Appropriate access design required due to proximity of Ysgol Cynfran | 40 | ||
Main villages: Tier 2 | ||||||||
Betws-yn-Rhos | ||||||||
92/274 | Minafon | 1.02 | 10 | Green | Improvements required to sewage treatment works. | 10 | ||
91/284 | Ffordd Llanelwy | 0.53 | 10 | Green | Improvements required to sewage treatment works. | 10 | ||
Cerrigydrudion | ||||||||
453 | Land fronting B5105 | 2.51 | 20 | Green | No major constraints | 20 | ||
Dolgarrog | ||||||||
470 | Tan y Ffordd, | 1.7 | 15 | Brown | New access will be required; works needed due to changes in level. | 15 | ||
Talybont waste treatment works need improving; low water pressure in the area. | ||||||||
MS25 | Aluminium works | 20.34 | 30 | Brown | Part of site C1, therefore this area should be excluded from development, as set out in the SFCA. Talybont waste treatment works need improving; low water pressure in the area. | 30 | ||
Eglwysbach | ||||||||
60 | Off Heol Martin | 0.64 | 10 | Green | Part of site at C2 flood risk. This should be avoided and/or mitigation measures put in place as set out in the SFCA. | 10 | ||
Any new development will require emergency access. | ||||||||
Improvements needed to sewage treatment works. | ||||||||
Llanfair TH | ||||||||
454 | The Smithy | 1.14 | 25 | Brown | Improvements to access required. | 25 | ||
Sewerage network and treatment works need improvement. | ||||||||
Llangernyw | ||||||||
277 | Coed Digain | 1 | 25 | Green | Some highway improvements required. | 25 | ||
Llansannan | ||||||||
289 | North of Llansannan | 1.05 | 25 | Green | Improvements needed to sewage treatment works | 25 |
Table 12: Conwy Housing Delivery and Phasing Plan: Contingency Sites
Urban Development Strategy Area | |||||
Site Ref | Site Name | Area | Number of units | PDL | Planning status |
(ha) | status | ||||
Abergele | |||||
78 | Llanfair Rd, Abergele | 3 | 100 | Green | Dependant on contributions towards a Traffic Improvement Scheme / annual monitoring of traffic flows within the town. |
Colwyn Bay | |||||
67 | Glyn Farm, Colwyn Bay | 0.9 | 27 | Green | New water main required |
502 | Llysfaen Road, Old Colwyn | 0.67 | 20 | Green | No major constraints |
Conwy, Llandudno | |||||
SR43 | Henryd Rd, Gyffin | 0.65 | 10 | Green | No major constraints |
SR85 | Nant-y-Gamar Road | 1.76 | 60 | Green | No major constraints |
37/38 | Off Derwen Lane, Penrhyn Bay | 5.06 | 175 | Green | Improvements to sewerage network required. |
Llanfairfechan, Penmaenmawr | |||||
384 | W of Penmaen Park, Llanfairfechan | 2.43 | 45 | Green | Site may be affected by possible A55 J15 changes. Some issues with ground level for access. |
135 | Conway Road, Penmaenmawr | 0.4 | 15 | Green | No major constraints |
Llanrwst | |||||
457 | Site C North East of Llanrwst | 3 | 70 | Green | Improvements needed to sewerage network and sewage works. |
Poor access. |
5.6 Employment Phasing and Delivery
5.6.1 Policy EMP/2 – ‘Allocation of New B1, B2 & B8 Office and Industrial Employment Development Sites’ states that the Council will plan, monitor and review the delivery of approximately 20.5 hectares of employment land (17.5 hectares in the Urban Development Strategy Area and 3 hectares in the Rural Development Strategy Area) with a contingency level of up to 1.5 hectares in the Urban Development Strategy area and 0.5 hectare in the Rural Development Strategy Area over the Plan period to meet the predicted change in population.
5.6.2 A further additional land requirement of 15.5 hectares, with a contingency of 1.5 hectares in addition, will be accommodated in the Urban Development Strategy Area to contribute to the reduction in out-commuting levels and to take account of bringing empty homes back into use.
5.6.3 It is important to note the difference between the provision of up to 22.5 hectares based on demand generated by predicted population change and up to 17 hectares based on demand generated to reduce out-commuting levels. Further explanation of these figures is provided in section 4.3 ‘The Economic Strategy’ (and associated policies) as well as Background Papers 13 – ‘Employment Land Monitoring Report’,14 – ‘Employment Land Study’ and 42 – ‘Employment Land Demand and Supply’.
5.6.4 Table 13 sets out the phasing plan for the delivery of employment land during the Plan period. As explained in BP/14, there will be greater demand and a shift towards B1 and B8 uses in the short to medium terms of the Plan period and B2 use in the longer term. The phasing of employment land has taken this factor into account, however, there are also interrelated issues regarding housing availability and infrastructure. Employment development is subject to the same restrictions outlined in the housing phasing sections (apart from Education), however, energy supply requirements are much harder to predict without knowing the precise details of business needs.
5.6.5 Conwy, in particular the Urban Development Strategy Area, experiences a high level of committed employment sites. The committed sites have all been phased for the short to medium period as the principle of development has been established and, in some cases, commenced. New sites have been split according to B1/B8 and B2 demand based on BP/14 and deliverability constraints identified in BP/21 – ‘Site Deliverability Assessment.’
5.6.6 As with the deliverability of housing sites, employment contingency sites have also been identified, outlined in EMP/2 and table 14 below. These sites are not allocated in the LDP, however, they have been identified in BP/21 and BP/41 as sites which could be developed should any site(s) in table 13 not come forward when anticipated. The release of any contingency sites will be in line with the trigger points identified in EMP/2 and the monitoring framework, which will be included in the Annual Monitoring Report. A trigger level for review of the delivery of employment land has therefore been identified and, depending on the issues and location, one of the sites in table 14 below could be brought forward during the Plan Period.
Table 13 Conwy Employment Land Phasing Plan
URBAN DEVELOPMENT STRATEGY AREA | ||||||||
Location | Total Land Area ha | Status | B1/B8 | B2 | ||||
SITES (Constructed, Under Construction, Committed and New Allocations) | Short Term 2007 - 2012 | Medium Term 2012 - 2017 | Long term 2017 - 2022 | Short Term 2007 - 2012 | Medium Term 2012 - 2017 | Long term 2017 - 2022 | ||
Mochdre Commerce Park | 10.5 (B1, B2 & B8) | Completed 2010/ Committed | 2.5 completed | 1.5 completed | 6.0 total 1.5 completed | 0.5 completed | ||
Land at Ffordd Maelgwyn, Llandudno Junction | 0.3 (B2) | Completed 2010 | 0.3 completed | |||||
Hotpoint, Narrow Lane, Llandudno Junction | 3.7 (B1) | Completed 2010 | 3.7 completed | |||||
Former Dairy, Station Road, Mochdre | 0.7 (B1 & B8) | Committed | 0.7 | |||||
Lynx Express, Penrhyn Avenue, Links Road, Rhos on Sea | 0.13 (B1) | Committed | 0.13 | |||||
Llandudno ‘on line’, Conway Road, Llandudno Junction | 3.2 (B1 & B2) | Committed | 1.0 | 2.2 | ||||
Unit 1, Morfa Conwy Business Park, Conwy | 0.2 (B1 & B8) | Completed 2010 | 0.2 completed | |||||
Ty Gwyn, Llanrwst | 1.54 (B1,B2 & B8) | Committed | 0.4 | 0.3 | 0.84 | |||
Abergele Business Park (Phase 1) | 2.0 (B1) | Completed 2010 | 2.0 completed | |||||
Abergele Business Park (Phase 2) | 2.0 (B1) | New Allocation | 2.0 | |||||
Esgyryn, Llandudno Junction (Mixed use Employment/Housing site) | 5.2 (B1) | New Mixed-Use Allocation | 4.2 | 1.0 | ||||
Penmaen Road, Conwy | 0.5 (B1) | New Mixed-Use Allocation | 0.5 | |||||
North East of Former Goods Yard, Llandudno Junction | 0.4 (B1) | New Allocation | 0.4 | |||||
The former Goods Yard, Llandudno | 1.4 (B1) | New Allocation | 1.4 | |||||
Abergele South East (Mixed-use Housing and Employment) | 2.0 (B1) | New Allocation | 2.0 |
RURAL DEVELOPMENT STRATEGY AREA | ||||||||
Location | Total Land Area ha | Status | B1/B8 | B2 | ||||
SITES (Constructed, Under Construction, Committed and New Allocations) | Short Term 2007 - 2012 | Medium Term 2012 - 2017 | Long term 2017 - 2022 | Short Term 2007 - 2012 | Medium Term 2012 - 2017 | Long term 2017 - 2022 | ||
MS9 Orme View Filling Station, Dwygyfylchi (Tier 1 Main Village) | 0.5 (B1/B2/B8) | New Allocation |
0.2 |
< 0.3 | ||||
Land at Memorial Hall, Dolgarrog (Tier 2 Main Village) | 0.3 (B1/B2/B8) | New Allocation | 0.3 | |||||
Site R30, Llansannan (Tier 2 Main Village) | 1.0 (B1/B2/B8) | New Allocation | 0.6 | 0.4 | ||||
Site R44, Llangernyw (Tier 2 Main Village) | 0.3 (B1/B2/B8) | New Allocation | 0.2 | 0.1 | ||||
Site R5 off B1505, Cerrigydrudion (Tier 2 Main Village) | 1.0 (B1/B2/B8) | New Allocation | 0.3 | 0.2 | 0.3 | 0.2 | ||
TOTAL SUPPLY | 8.4 | 11.83 | 3.4 | 1.8 | 9.2 | 2.24 |
Table 14 Employment Land Contingency Sites
Location | Proposed Site | Use | Size |
Urban Development Strategy Area | Abergele South East | BI/B2/B8 | 3.7 Ha |
TOTAL URBAN CONTINGENCY SUPPLY | 3.7 Ha | ||
Rural Development Strategy Area | MS9 Orme View Filling Station, Dwygyfylchi (Tier 1 Main Village, Rural) | B1/B2/B8 | 0.5 Ha |
TOTAL RURAL CONTINGENCY SUPPLY | 0.5 Ha | ||
TOTAL CONTINGENCY SUPPLY | 4.2 Ha |
5.7 Implementation Plan
5.7.1 The Implementation Plan shows how particular policies will be implemented and which agencies will contribute towards this. In many cases the detailed implementation of the policies will be via allocations and policies as shown in Table 15 below. In other instances, an SPG, such as LDP4 – ‘Planning Obligations’ SPG, Development Briefs, and LDP10 – ‘Colwyn Bay Masterplan’ SPG, will provide more detailed implementation of the policies. However in many other cases the delivery depends on integrated working with other agencies and partnerships. Conwy County Borough Council are actively involved in several delivery partnerships such as the Local Service Board (LSB), which brings together service providers to work in a co-ordinated way.
5.7.2 A key factor to the delivery of the LDP policies is the provision of vital infrastructure required for new development. Infrastructure providers have indicated a range of constraints in Conwy (detailed in Section 5.3 and in BP/21) and development has been phased in accordance with the likely funding and programme of works anticipated at this time (see tables 11 and 12 in the previous section). If infrastructure is able to be provided ahead of anticipated timescales, or alternative supply such as renewable energy can be provided, then development may be able to be provided earlier than shown in the housing trajectory.
5.7.3 The policies on Development Criteria (DP/4) and Infrastructure and New Developments (DP/5) are key to infrastructure provision. However, in some cases utility providers need to complete a programme of facility upgrading before development can take place. At present the planning obligations protocol administered by Conwy County Borough Council provides for funding for education, library, fire hydrants and social service provision. Transport infrastructure improvements are negotiated individually, based on the transport impacts of the development. The Government is also considering the introduction of a Community Infrastructure Levy which would require the uplift of value in land on obtaining planning permission to be used for community benefits. At present the details of how such a scheme might work in practice are unclear. However, the LDP acknowledges that the way planning obligations, community benefits and infrastructure improvements are provided is likely to change during the lifetime of the Plan. These changes will be reflected in updates to the SPG on Planning Obligations, which will include AHLN contributions. This may have an impact in relation to the timing of large scale infrastructure upgrading programmes.
5.7.4 Table 15 ‘Implementation Plan’ shows how particular policies will be implemented and which agencies will contribute towards this.
Table 15 Implementation Plan
LDP Policy | Implementation Mechanism | Responsible Agencies/Partners | Dependencies | Contingencies | Risks | Mitigation |
Spatial Strategy | ||||||
The Spatial Strategy for Conwy |
|
|
The delivery of development needs is also dependent on the construction of various infrastructure requirements. | Phase development accordingly and identify Greenfield contingency sites in the LDP Undertake early review of the Preferred Strategy to assess delivery and site requirements. Phase development to ensure that supporting infrastructure is available. |
There is a risk that further constraints on land within the Urban Development Strategy Area could have an impact on delivery and take-up of Brownfield/ Greenfield sites, especially relating to overall cost of delivery Availability of Government/ Regional funding. Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. |
Look to the sequential test and settlement hierarchy in DP/2. Planning Obligations SPG and other developer negotiation tools to promote transparency. Development of contingency sites in line with the sequential test and settlement hierarchy. Lobbying Apply an element of contingency to the housing delivery to take account of certain sites potentially not coming forward. Reviews and Monitoring through the AMR |
Development Principles | ||||||
DP/1 Sustainable Development Principles |
|
|
A public and private partnership approach | Phasing of Development, lobbying of government for funding and allocation of contingency sites | There is a risk that further constraints on land within the Urban Development Strategy Area could have an impact on delivery and take-up of Brownfield/Greenfield sites, especially relating to overall cost of delivery Availability of Government/Regional funding. Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. |
Ensure that the LDP is flexible enough to deal with changing circumstances and that at least priority issues, such as AHLN are delivered Look to the sequential test and settlement hierarchy in DP/2. Reviews and Monitoring through the AMR |
DP/2 Overarching Strategic Approach |
|
|
Dependent on the delivery of the majority of the development needs in the Urban Development Strategy Area | Phasing of Development, lobbying of government for funding and allocation of contingency sites | Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. | Sequential test policy Government Lobbying for funding to overcome the issue Apply an element of contingency to the housing and employment delivery to take account of certain sites potentially not coming forward Reviews and Monitoring through the AMR |
DP/3 Promoting Design Quality and Reducing Crime |
|
|
Dependent on the strength of the policies, viability and a partnership approach. | Design SPG Annual Monitoring of the policy to ensure delivery. Flexible policies. |
Policy not being fully implemented. | Ensure monitoring through the Conwy Annual Monitoring Report (AMR) and amend the policy where appropriate to ensure design quality. Encourage pre-application discussions |
DP/4 Development Criteria and DP/5 Infrastructure and New Developments |
|
|
Low Land Values and land with no constraints | Flexibility in the Developer Contributions policy to aid the delivery of needs and overcome deprivation and high unemployment. Prioritise requirements and produce developer negotiation tools to promote transparency. |
High Land Values and land with significant constraints. | Flexibility in what is contributed dependent on overall site requirements and cost. Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Apply an element of contingency to the housing and employment delivery to take account of certain sites potentially not coming forward Use the Three Dragons Tool Kit to undertake an early assessment of the likely contributions on and off site. Reviews and Monitoring through the AMR |
DP/6 National Planning Policy and Guidance |
|
|
Up to date Guidance | None | None | None |
DP/7 Masterplans and Community Appraisals |
|
|
Dependent on funding opportunities | Annual Monitoring of the policy to ensure delivery. | Availability of Government/Regional funding. | Reviews and Monitoring through the AMR Government Lobbying for funding to overcome the issue and CPO Powers |
DP/8 Colwyn Bay Urban Regeneration Masterplan |
|
|
Dependent on funding opportunities | Annual Monitoring of the policy to ensure delivery. | Availability of Government/Regional funding. | Reviews and Monitoring through the AMR Government Lobbying for funding to overcome the issue and CPO Powers |
The Housing Strategy | ||||||
HOU/1 Meeting the Housing Need |
|
|
Dependent on the delivery of current permissions in the short-term and the majority of delivery in the Urban Development Strategy Area in the longer-term. Dependent on the provision of infrastructure to realise the delivery of the housing needs. |
Early review of the LDP Preferred Strategy, the identification of contingency sites in the LDP and sequential test policy. | Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. Constraints on site may prevent the delivery of key infrastructure and community facilities. |
Contingency sites CPO Powers Flexibility in what is contributed dependent on overall site requirements and cost. Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Use the Three Dragon s Tool Kit to undertake an early assessment of the likely contributions on and off site. Reviews and Monitoring through the AMR |
HOU/2 Affordable Housing for Local Need HOU/3 Phasing Housing Development HOU/4 Housing Density HOU/5 Housing Mix HOU/6 Exception Sites for AHLN HOU/7 Council and Government Owned Sites in the Plan Area HOU/8 Register of Land Holdings |
|
|
Dependent on funding from Registered Social Landlords/Housing Associations to ensure delivery of the high AHLN requirement | Housing policy, exception sites and early developer negotiation tools. | Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. | Reviews and Monitoring through the AMR including the release of contingency sites where required Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site |
HOU/9 Gypsies and Travellers |
|
|
Dependent on site search & appraisal, Council agreement to progression & determination of planning application within timescale | If no Council Agreement to findings of site search/submission/ determination of planning application within timescale LPA to commence Plan Review | Lack of Council agreement to search findings / failure to submit or determine within timescales, or refusal of planning permission | Reviews and Monitoring through the AMR & early plan review to commence (with allocation of site) if LPA fail to identify a site or planning permission is not granted within timescales |
HOU/10 Houses in Multiple Occupation and Self Contained Flats. |
|
|
Dependent on up to date monitoring | None | Policy not being fully implemented. | Reviews and Monitoring through the AMR |
HOU/11 Residential Care Homes and Extra Care Housing |
|
|
Dependent on the identification of need | None | None | Reviews and Monitoring through the AMR |
HOU/12 Re-use and adaptation of redundant rural buildings for residential use |
|
|
Dependent on up to date monitoring and funding from Registered Social Landlords/ Housing Associations | Housing policy, exception sites and early developer negotiation tools. | Under current housing markets, the house building industry may decline with an impact on delivery of the LDP. | Reviews and Monitoring through the AMR. Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Use the Three Dragons Tool Kit to undertake an early assessment of the likely contributions. |
Employment Strategy | ||||||
EMP/1 Meeting the Employment Needs |
|
|
Dependent on the delivery of current committed employment permissions. | Early review required and sequential test policy. Flexibility |
Committed sites do not come forward | Ensure that there is constant review and monitoring to bring forward sites and overcome delivery constraints. Reviews and Monitoring through the AMR including the release of contingency sites where required |
EMP/2 Allocation of new B1, B2 and B8 Office and Industrial Employment Development Sites EMP/3 New B1, B2 and B8 Office and Industrial Development on Non Allocated Sites |
|
|
Dependent on the delivery of current committed employment permissions. | Early review required and sequential test policy. Flexibility |
Flood risk issues may not be resolved on some committed sites, which will have an impact on delivery. | Ensure that there is constant review and monitoring to bring forward sites and overcome any delivery constraints. Reviews and Monitoring through the AMR |
EMP/ 4 Safeguarding existing B1, B2 & B8 Office and Industrial Sites EMP/5 Office and Industrial Employment Improvement Areas EMP/6 Re-use and Adaptation of Redundant Rural Buildings |
|
|
Dependent on strong policy and up to date monitoring through the AMR and the Employment Land Monitoring Report | AMR | None | Reviews and Monitoring through the AMR |
Tourism | ||||||
TOU/1 Sustainable Tourism TOU/2 New Sustainable Tourism and Recreational Development TOU/3 Holiday Accommodation Zone TOU/4 Chalet, Caravan and Camping Sites |
|
|
Holiday Accommodation Zones, Strategic and Rural Tourism Areas | Monitoring of designations to ensure they are up to date and appropriate. | None | Reviews and Monitoring through the AMR |
Community Facilities and Services | ||||||
CFS/1 Community Facilities and Services CFS/2 Retail Hierarchy |
|
|
Delivery of sites for Open Space. | Monitoring of designations to ensure they are up to date and appropriate. | Difficult to prevent the loss of further facilities in the rural areas | Undertake regular health checks of rural settlements to provide valuable data for development control and their decisions. Ensure regular updates of the Retail Study are undertaken to provide evidence of current demand and supply in Colwyn Bay and Llandudno Reviews and Monitoring through the AMR |
CFS/3 Primary Shopping Areas CFS/4 Shopping Zones |
|
|
Up to date designations and monitoring of retail uses within the zones | AMR/Retail Study and Zone Monitoring | Pressure from other uses. | Reviews and Monitoring through the AMR / Retail Study and Zone Monitoring |
CFS/5 Retail Parks |
|
|
Dependent on a strong policy and careful monitoring of retail uses within the retail parks | AMR Retail Study |
Pressure from other uses. | Reviews and Monitoring through the AMR |
CFS/6 Safeguarding of Community Facilities outside the sub-regional centre and the town centres |
|
|
Up to date policy. Dependent on the delivery of housing development and partnership working with relevant bodies. |
Annual Monitoring Report and Village Services and Facilities monitoring. | Difficult to prevent the loss of further facilities in Conwy | Undertake regular health checks of Conwy and review the policy through the AMR and updated Retail Studies. Undertake regular health checks of rural settlements to provide valuable data for development control and their decisions. |
CFS/7 Shop Front Design CFS/8 Shop Front Security |
|
|
Implementation of the SPG | None | None | None |
CFS/9 Safeguarding Allotments CFS/10 New Allotments |
|
|
Up to date policy and monitoring of supply and demand. | Annual Monitoring Report, Village Services and Facilities monitoring survey and Planning Obligations SPG | Unable to prevent the loss of community facilities in the rural area. | Reviews and Monitoring through the AMR |
CFS/11 Development and Open Space CFS/12 Safeguarding Existing Open Space CFS/13 New Open Space Allocations |
|
|
Up to date policy. Dependent on the delivery of housing development and partnership working with relevant bodies. |
Annual Monitoring Report, Village Services and Facilities monitoring survey and Planning Obligations SPG | Unable to prevent the loss of community facilities in the rural area. | Reviews and Monitoring through the AMR Undertake regular health checks of rural settlements to provide valuable data for development control and their decisions. |
CFS/14 New Burial Ground Allocations |
|
|
Up to date policy and monitoring of supply and demand. | Annual Monitoring Report | None | Reviews and Monitoring through the AMR |
CFS/15 Education Facilities |
|
|
Up to date policy. Dependent on the delivery of housing development and partnership working with relevant bodies. |
Annual Monitoring Report | None | Reviews and Monitoring through the AMR |
The Natural Environment | ||||||
NTE/1 The Natural Environment NTE/2 Green Wedges and Meeting the Development Needs of the Community NTE/3 Biodiversity NTE/4 The Landscape and Protecting Special Areas NTE/5 The Coastal Zone |
|
|
Dependent on the developer contributions to manage, conserve and enhance sites | Planning Obligations SPG and partnership working | Policy not being fully implemented. | Use the Three Dragons Tool Kit to undertake an early assessment of the likely contributions on and off site. Reviews and Monitoring through the AMR |
NTE/6 Energy Efficiency and Renewable Technologies in New Development NTE/7 Onshore Wind Turbine Development |
|
|
Dependent on the delivery of development, which meets the renewable energy targets of the policy. | Monitor policy through the AMR and produce early negotiation tools for developers on the Council’s requirements. | Further constraints on site which has an impact on the deliverability in financial terms. | Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Reviews and Monitoring through the AMR |
NTE/8 Sustainable Drainage Systems NTE/9 Foul Drainage NTE/10 Water Conservation |
|
|
Dependent on the delivery of development | Monitor policy through the AMR and produce early negotiation tools for developers on the Council’s requirements. | Further constraints on site which has an impact on the deliverability in financial terms. | Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Reviews and Monitoring through the AMR |
Cultural Heritage | ||||||
CTH/1 Cultural Heritage CTH/2 Development Effecting Heritage Assets CTH/3 Buildings and Structure of Local Importance CTH/4 Enabling Development |
|
|
Implementation of policy and SPG | Monitor policy through the AMR and produce early negotiation tools for developers on the Council’s requirements. | Policy not being fully implemented. | Enforcement Procedures Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Reviews and Monitoring through the AMR |
CTH/5 The Welsh Language |
|
|
Implementation of the Welsh Language SPG | Ensure that the impact of the proposed development has been fully covered in the Community and Linguistic Statement or Impact Assessments and Mitigation Statements required, in line with policy thresholds | Policy not being fully implemented. | Reviews and Monitoring through the AMR Development Control Process |
Sustainable Transport | ||||||
STR/1 Sustainable Transport, Development and Accessibility STR/2 Parking Standards SPG STR/3 Mitigating Travel Impact STR/4 Non-Motorised Travel STR/6 Rail Freight |
|
|
Dependent on funding and developer contributions from development. | None | Risk to raising the appropriate level of funding for larger infrastructure dependencies. High Land Values and land with significant constraints. |
Developer Contributions Flexibility in what is contributed dependent on overall site requirements and cost. Undertake early consultation with statutory bodies to identify constraints and the deliverability of the site. Use the Three Dragons Tool Kit to undertake an early assessment of the likely contributions on and off site. CPO Powers Regional Transport Plan. |
STR/5 Integrated Sustainable Transport System | Forydd Harbour dual-use Bridge |
|
Funding | Partnership Working to establish developer contributions, SUSTRANS funding and Lottery funding. | Lack of Funding | Partnership Working to establish developer contributions, SUSTRANS funding and Lottery funding. |
Llandudno Junction Integrated Footbridge |
|
Funding | Partnership Working to establish developer contributions. | Lack of Funding | Partnership Working to establish developer contributions, | |
Llandudno Sustainable Transport Interchange Facility |
|
Funding | Partnership Working to establish funding and developer contributions. | Lack of Funding | Partnership Working to establish funding and developer contributions, | |
Minerals and Waste Strategy | ||||||
MWS/1 Minerals and Waste MWS/2 Minerals MWS/3 Safeguarding Hard Rock and Sand and Gravel Resources MWS/4 Quarry Buffer Zones |
|
|
The local Quarry industry to deliver demand. Up to date designations |
Allocation of sites | Policy not being fully implemented. | Reviews and Monitoring through the AMR Development Control Process |
MWS/5 Proposals for Waste Management MWS/6 Locations for Waste Management Facilities MWS/7 Use of Industrial Land for Waste Management Facilities MWS/ 8 Landfill Buffer Zone |
|
|
Dependant on the extension/ retention of existing sites. Dependant on developer contributions |
Reasoning and Justification for the allocation of the Sites Planning Obligations SPG |
Policy not being fully implemented. | Reviews and Monitoring through the AMR Development Control Process |