There is no comment on the fact that some of the previously allocated sites may have in fact been the wrong sites to allocate, particularly any rolled over from previous plans.
No account taken of the issues identified in the WG Longitudinal and Viability study regarding site viability and deliverability.

Testun llawn:

There has been no discussion about one of the other factors which has affected the provision of housing, which is around the suitability of the sites allocated. Although it is accepted that the allocated sites went through a degree of scrutiny as part of their allocation in the LDP, the recent WG study entitled 'Longitudinal Viability Study of the Planning Process' has highlighted the need to look at deliverability and viability far more closely than it has been in previous LDP's. The HBF would request an additional paragraph which refers to this study and looks at the issues from the report referred to above in more detail thus giving a more balance view.


Ein hymateb:

Noted. This will be considered as part of the LDP Review.

Sylw

Adroddiad Adolygu

ID sylw: 27187

Derbyniwyd: 21/12/2017

Ymatebydd: Dwr Cymru Welsh Water

Crynodeb o'r Gynrychiolaeth:

We note that the Review will need to reconsider both the scale and distribution of growth proposed, and that the capacity of settlements to absorb additional employment and residential development will need to be assessed in light of the evidence to be collected through the Review. Since the LDP was adopted in 2013 it will be necessary for us to reassess the capacity of our infrastructure to accommodate growth.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted.

Cefnogi

Adroddiad Adolygu

ID sylw: 27188

Derbyniwyd: 21/12/2017

Ymatebydd: FCC Environmental (UK) Limited

Asiant : Axis

Crynodeb o'r Gynrychiolaeth:

The review should consider larger scale windfall developments and allocations within and adjacent to Tier 1 Villages in order to achieve shortfalls in the Rural Development Strategy Areas (RDSA) identified in paragraph 4.5.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. Housing policies will be re-assessed as part of the LDP Review process.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27207

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

Rather than the Review Report using language which suggests a need to reduce the housing supply the Council should be taking positive and continuing steps to enable delivery of housing, including in a replacement LDP.
Additional, suitable, viable land attractive to the market in sustainable places where people want to live is available and capable of contributing to housing delivery.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. Housing requirements and supply levels will be re-assessed as part of the Review process.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27212

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

There is no mention of the suitability of sites allocated for housing in the plan or indeed their potential to become available. For example there has been subsequent research on the need to look at deliverability and viability far more closely than in previously LDPs (WG study 'Longitudinal Viability Study of the Planning Process').
Furthermore case studies (including in Conwy) suggest permissions not being released as a result of delays in signing S106 agreements.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Accepted. As part of the LDP review, candidate sites will be required to demonstrate viability and deliverability before being allocated. The conclusion will be expanded to reflect this.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27225

Derbyniwyd: 22/12/2017

Ymatebydd: Beech Developments (NW) Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

Rather than the Review Report using language which suggests a need to reduce the housing supply the Council should be taking positive and continuing steps to enable delivery of housing, including in a replacement LDP.
Additional, suitable, viable land attractive to the market in sustainable places where people want to live is available and capable of contributing to housing delivery.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. Housing requirements and supply levels will be re-assessed as part of the Review process.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27230

Derbyniwyd: 22/12/2017

Ymatebydd: Beech Developments (NW) Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

There is no mention of the suitability of sites allocated for housing in the plan or indeed their potential to become available. For example there has been subsequent research on the need to look at deliverability and viability far more closely than in previously LDPs (WG study 'Longitudinal Viability Study of the Planning Process').
Furthermore case studies (including in Conwy) suggest permissions not being released as a result of delays in signing S106 agreements.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Accepted. As part of the LDP review, candidate sites will be required to demonstrate viability and deliverability before being allocated. The conclusion will be expanded to reflect this.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27243

Derbyniwyd: 22/12/2017

Ymatebydd: Macbryde Homes Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

Rather than the Review Report using language which suggests a need to reduce the housing supply the Council should be taking positive and continuing steps to enable delivery of housing, including in a replacement LDP.
Additional, suitable, viable land attractive to the market in sustainable places where people want to live is available and capable of contributing to housing delivery.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. Housing requirements and supply levels will be re-assessed as part of the Review process.

Gwrthwynebu

Adroddiad Adolygu

ID sylw: 27248

Derbyniwyd: 22/12/2017

Ymatebydd: Macbryde Homes Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

There is no mention of the suitability of sites allocated for housing in the plan or indeed their potential to become available. For example there has been subsequent research on the need to look at deliverability and viability far more closely than in previously LDPs (WG study 'Longitudinal Viability Study of the Planning Process').
Furthermore case studies (including in Conwy) suggest permissions not being released as a result of delays in signing S106 agreements.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Accepted. As part of the LDP review, candidate sites will be required to demonstrate viability and deliverability before being allocated. The conclusion will be expanded to reflect this.