Gwrthwynebu
Adroddiad Adolygu
ID sylw: 27209
Derbyniwyd: 22/12/2017
Ymatebydd: Anwyl Construction Ltd
Asiant : P L Planning
Crynodeb o'r Gynrychiolaeth:
The LDP housing target was not unrealistic. It was evidence based, consulted upon at Deposit, Examined and found to be Sound. This should be explicitly acknowledged.
Testun llawn:
See attached document.
Ein hymateb:
Accepted in part. Whilst we acknowledge that the housing target was found sound at Examination, subsequent WG projections have indicated far lower housing requirements. The Inspector did not take into account the reduced level of delivery since 2008, although CCBC argued to reduce the requirement for this reason.