Adroddiad Adolygu

Chwilio sylwadau

Canlyniadau chwilio Anwyl Construction Ltd

Chwilio o’r newydd Chwilio o’r newydd

Gwrthwynebu

Adroddiad Adolygu

5.2.2

ID sylw: 27216

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

The UK has not been in recession since 2013. The Review report should reflect this and look to the other reasons (many of which are identified in full) why the plan has not delivered. Help to buy should be referred to in this section.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. It is acknowledged that the UK is no longer in recession, however the effects of the downturn are still being felt in the delivery of housing.

Gwrthwynebu

Adroddiad Adolygu

5.2.5

ID sylw: 27217

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

Other appeal decisions in the area have not been allowed despite the lack of five year land supply. A balanced view should therefore be given to avoid the wording suggesting housebuilders will be able to win any appeal - which is clearly not the case. The lack of success on appeal where the council has less than a five year land supply is a cross-Wales issue.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Not accepted. This paragraph does not suggest that appellants would win appeals for residential development in all cases. It clearly refers to the requirement for speculative development to 'otherwise comply with development plan and national policies'.

Sylw

Adroddiad Adolygu

5.2.8

ID sylw: 27218

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

It would be helpful to provide a table of developed sites along with the level of affordable housing achieved. Where below policy requirement provide a reason to give a balanced view.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted.

Sylw

Adroddiad Adolygu

5.2.9

ID sylw: 27219

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

Other Councils in north Wales now actively delivering affordable housing units through their own delivery vehicles and through the delivery to those companies of "gifted units" as part of developments. This provides early delivery to known needs.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted.

Gwrthwynebu

Adroddiad Adolygu

5.2.11

ID sylw: 27220

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

This additional affordable housing need should not automatically mean the Affordable Housing policy requirement will be set higher than previously. Viability is critical and any increase in affordable requirement may potentially reduce the overall number of houses delivered .

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. The Review Report does not state that AH percentages will increase. Affordable housing requirements and delivery mechanisms will be re-assessed as part of the LDP Review process.

Cefnogi

Adroddiad Adolygu

5.3.1

ID sylw: 27221

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

The developers strongly welcome and support full review of existing employment allocations to identify any that could be released to housing.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted. All undeveloped allocations will be reviewed and where appropriate considered for other uses as part of the LDP review process.

Gwrthwynebu

Adroddiad Adolygu

7.6

ID sylw: 27222

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

TAN1 is not the reason why the plan must be reviewed. TAN1 provides the nationally accepted measure of genuinely available housing land and performance again the plan. This paragraph should be reworded to acknowledged that housing land supply is constraint by a number of factors. It should also address the likely requirement for a Joint LDP with Denbighshire.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Not Accepted

Gwrthwynebu

Adroddiad Adolygu

8.1

ID sylw: 27223

Derbyniwyd: 22/12/2017

Ymatebydd: Anwyl Construction Ltd

Asiant : P L Planning

Crynodeb o'r Gynrychiolaeth:

The developers object to the conclusion that the way to measure and demonstrate improved performance in delivering homes is to seek fewer at the outside. Housing provision should be set taking account of the identified need as advised in PPW as well as providing for any economic or other aspirations linked to housing need. The plan must not set housing need at a low level just to allow for the numbers to be delivered.

Testun llawn:

See attached document.

Atodiadau:


Ein hymateb:

Noted.

Am gyfarwyddiadau ar sut I ddefnyddio’r system ac I wneud sylwadau, gwelwch ein canllaw cymorth.