Gwrthwynebu
Cofrestr o Safleoedd Ymgeisiol
ID sylw: 27678
Derbyniwyd: 20/09/2019
Respondent ID: 6492
Ymatebydd: Mr Ricky Carter
The land identified as Site 58 has caused significant and costly off site flooding of Aber Road and adjacent properties. During such events, the highway has been impassable, impacting both on residents, and the emergency services. TAN 15 (paragraph 10.4) " ....flood risk will be a material factor in the formulation of specific policies and allocation of sites". Other than generic reference to SuDS, there has been no specific flood mitigation measures proposed, nor the consideration of the implications of climate change. As such it is considered that the allocation of this site is considered premature.
Not accepted. The site has been sent to Natural Resources Wales for specific comments regarding flooding. Their comments will include if there is likely to be any impact on neighbouring areas. The Replacement LDP and all the sites which are to be allocated will be subject to a Floods Consequences Assessment.