5.2.4
Comment
Review Report
Representation ID: 27163
Received: 22/12/2017
Respondent: Home Builders Federation Ltd
If any of the suggested changes already made in response to earlier sections of the document are made then this paragraph will also need to be amended particularly around the fact it blames the recession as the main reason for not achieving a 5 year land supply. Reference should also be made to the WG study 'Longitudinal Viability Study of the Planning Process' in this paragraph.
If any of the suggested changes already made in response to earlier sections of the document are made then this paragraph will also need to be amended particularly around the fact it blames the recession as the main reason for not achieving a 5 year land supply. Reference should also be made to the WG study 'Longitudinal Viability Study of the Planning Process' in this paragraph.
Noted.
Comment
Review Report
Representation ID: 27172
Received: 28/11/2017
Respondent: Town and Country Planning Services (Conwy)
A review of the land allocations is overdue and there is evidence of local hoarding of land to the disadvantage of other applicants. Only genuine sites over 10 units should be retained and contingency sites removed.
I support a review of the boundaries.
The rural settlement strategy requires review.
I would like the LDP to set an upper limit on any site attempting to circumvent the LDP at 20 dwellings.
A review of green barriers should link in with this work.
Housing allocations in Llanfairfechan need to be updated.
Colwyn Bay housing supply needs increasing.
See attached document.
Noted. Amendments to policies will be considered as part of the LDP Review process.
Support
Review Report
Representation ID: 27189
Received: 21/12/2017
Respondent: FCC Environmental (UK) Limited
Agent: Axis
Housing land allocations should be reviewed and new deliverable sites allocated
through a call for candidate sites. In addition, windfall site and allocations within and adjacent to in Tier 1 villages should not be capped in size as this limits the ability of the market to deliver housing where there is a demand and which otherwise would be consistent with the thrust of the LDP.
See attached document.
Noted. Amendments to policies will be considered as part of the LDP Review process.